| |
Materials
and Resources
|
Credit |
Description |
|
Prereq 1
Storage and Collection of Recyclables
Required
|
Intent:
To facilitate the reduction
of waste generated by building occupants
that is hauled to and disposed of in
landfills.
Requirements:
Provide an easily
accessible dedicated area for the collection
and storage of materials for recycling for
the entire building. Materials must include
at a minimum paper, corrugated cardboard,
glass, plastics and metals.
Implementation:
Building owners and
designers must determine the best way to
create a dedicated recycling collection and
storage area that is easily accessible
within the building and encourages recycling
yet is accessible to the waste hauler.
Recyclable material collection and storage
space might increase the project footprint
in some instances. Consider how recycling
activities might affect a building's indoor
environmental quality. Activities that
create odors, noise and air contaminants
should be isolated or performed during
nonoccupant hours. The requirements of this
prerequisite do not regulate the size of the
recycling area. However, the table below
provides guidelines for the recycling
storage area based on overall building
square footage, including corridors,
elevators, stairwells and shaft spaces.
These guidelines will help the design team
to determine the appropriate size for
recycling facilities according to specific
building operations.
|
Commercial Building (sf) |
Minimum Recycling Area (sf) |
| 0 to
5,000 |
82 |
| 5,001
to 15,000 |
125 |
|
15,001 to 50,000 |
175 |
|
50,001 to 100,000 |
225 |
|
100,001 to 200,000 |
275 |
|
200,001 or greater |
500 |
|
|
MR 1.1
Building Reuse - Maintain Existing Walls,
Floors and Roof
1-3 points
|
Intent:
To extend the life cycle of
existing building stock, conserve resources,
retain cultural resources, reduce waste and
reduce environmental impacts of new
buildings as they relate to materials
manufacturing and transport.
Requirements:
Maintain the existing
building structure (including structural
floor and roof decking) and envelope (the
exterior skin and framing, excluding window
assemblies and nonstructural roofing
material). Hazardous materials that are
remediated as a part of the project must be
excluded from the calculation of the
percentage maintained. The minimum
percentage building reuse for each point
threshold is as follows:
|
Building Reuse |
Points |
| 55% |
1 |
| 75% |
2 |
| 95% |
3 |
If the new project includes an addition that
is more than 2 times the square footage of
the existing building, this credit is not
applicable.
Implementation:
If the project will
reuse part of an existing building,
inventory the existing conditions. The
architect should develop a floor plan
showing the location of existing structural
components, exterior and party walls, and
exterior windows and doors. The drawings
should be detailed enough to determine the
surface area of all elements to be reused.
Confirm that the structural and envelope
elements designated for reuse can be reused
and take the necessary steps to retain and
maintain them. Projects that incorporate
part of an existing building but do not meet
the requirements of MR Credit 1 may apply
the reused portion toward the achievement of
MR Credit 2, Construction Waste management.
To do so, determine an approximate weight or
volume for existing building elements. |
|
MR 1.2
Building Reuse - Maintain Interior
Nonstructural Elements
1 point
|
Intent:
To extend the life cycle of
existing building stock, conserve resources,
retain cultural resources, reduce waste and
reduce environmental impacts of new
buildings as they relate to materials
manufacturing and transport.
Requirements:
Use existing interior
nonstructural elements (e.g., interior
walls, doors, floor coverings and ceiling
systems) in at least 50% (by area) of the
completed building, including additions. If
the new project includes an addition that is
more than 2 times the square footage of the
existing building, this credit is not
applicable.
Implementation:
Confirm that the
items designated for reuse can be reused and
take the necessary steps to retain and
maintain them in the finished work. Fixed
items, such as nonstructural walls and
doors, are included in this credit and count
toward the percentage of reuse when they
perform the same function (e.g., doors
reused as doors). If materials are used for
another purpose (e.g., doors made into
tables), they can count toward the
achievement of MR Credit 3, Materials Reuse,
but they cannot count toward both credits.
Projects that incorporate part of an
existing building but do not meet the
requirements of MR Credit 1 may apply the
reused portion toward the achievement of MR
Credit 2, Construction Waste management. To
do so, determine an approximate weight or
volume for existing building elements. |
|
MR 2
Construction Waste Management
1-2 points
|
Intent:
To divert construction and
demolition debris from disposal in landfills
and incineration facilities. Redirect
recyclable recovered resources back to the
manufacturing process and reusable materials
to appropriate sites.
Requirements:
Recycle and/or salvage
nonhazardous construction and demolition
debris. Develop and implement a construction
waster management plan that, at a minimum,
identifies the materials to be diverted from
disposal and whether the materials will be
sorted on-site or comingled. Excavated soil
and land-clearing debris do not contribute
to this credit. Calculations can be done by
weight or volume, but must be consistent
throughout. The minimum percentage debris to
be recycled or salvaged for each point
threshold is as follows:
|
Recycled or Salvaged |
Points |
| 50% |
1 |
| 75% |
2 |
Implementation:
This credit addresses
how much waste material leaving the site is
diverted from landfills. the percentage
requirement represents the amount diverted
through recycling and salvage divided by the
total waste generated by the construction
project.
Identify construction haulers and recyclers
to handle the designated materials; they
often serve as valuable partners in this
effort. Make sure that job-site personnel
understand and participate in construction
debris recycling, and ask them to provide
updates throughout the construction process.
Obtain and retain verification records
(e.g., waste haul receipts, waste management
reports and spreadsheets) to confirm that
the diverted materials have been recycled or
salvaged as intended. Diversion may include
salvaged materials such as furniture,
computers and equipment, white boards,
lockers, doors, lighting and plumbing
fixtures. Salvaged material can be donated
to charitable organizations such as Habitat
for Humanity, reuse centers, nonprofit
organizations or other buildings. Materials
sold to the community can also be counted.
A project may choose to separate
construction waste on-site or have comingled
construction waste sorted at an off-site
facility. On-site separation provides
immediate feedback of the ongoing waste
diversion efforts, but may require
additional labor. Although comingled
recycling can increase recycling costs, it
might also simplify the waste management
effort on-site and ensure that diversion
rates will be high. This option is
especially useful for projects with tight
space constraints and no room for multiple
collection bins. |
|
MR 3
Materials Reuse
1-2 points
|
Intent:
To reuse building materials
and products to reduce demand for virgin
materials and reduce waste, thereby
lessening impacts associated with the
extraction and processing of virgin
resources.
Requirements:
Use salvaged,
refurbished or reused materials, the sum of
which constitutes at least 5% or 10%, based
on cost, of the total value of materials on
the project. The minimum percentage of
materials reused for each point threshold is
as follows:
|
Reused Materials |
Points |
| 5% |
1 |
| 10% |
2 |
Mechanical, electrical and plumbing
components, and specialty items such as
elevators and equipment cannot be included
in this calculation. Include only materials
permanently installed in the project.
Furniture may be included if it is included
consistently in MR Credit 3: Materials Reuse
through MR Credit 7: Certified Wood.
Implementation:
Using salvaged and
refurbished materials in building projects
extends the life of materials and can reduce
overall initial costs. Use of salvaged
materials can also add character to the
building and can be used effectively as
architectural details.
Reused Materials Found On-site -
Items that were "fixed" components on-site
before construction began. To qualify for
this credit, these items must no longer be
able to serve their original functions and
must then be installed for a different use
or in a different location. An example would
be a door removed and modified to serve as
the countertop for the receptionist station.
Reused Materials Found Off-site -
Reusable materials eligible for this credit
are not limited to items found within the
project building. Materials obtained
off-site qualify as reused if they have been
previously used. These materials may be
purchased as salvaged, similar to any other
project material, or they may be relocated
from another facility, including ones
previously used by the occupant. The
salvaged materials from both on-site and
off-site can be applied to MR Credit 5,
Regional Materials, if they comply with the
requirements of that credit. Materials
qualifying as reused for MR Credit 3 cannot
be applied to MR Credits 1,2,4,6 or 7. |
|
MR 4
Recycled Content
1-2 points
|
Intent:
To increase demand for
building products that incorporate recycled
content materials, thereby reducing impacts
resulting from extraction and processing of
virgin materials.
Requirements:
Use materials with
recycled content such that the sum of
postconsumer recycled content plus 1/2 of
the preconsumer content constitutes at least
10% or 20%, based on cost, of the total
value of the materials of the project. The
minimum percentage materials recycled for
each point threshold is as follows:
|
Recycled Content |
Points |
| 10% |
1 |
| 20% |
2 |
The recycled content value of a material
assembly is determined by weight. The
recycled fraction of the assembly is then
multiplied by the cost of assembly to
determine the recycled content value.
Mechanical, electrical and plumbing
components, and specialty items such as
elevators cannot be included in this
calculation. Include only materials
permanently installed in the project.
Furniture may be included if it is included
consistently in MR Credit 3: Materials Reuse
through MR Credit 7: Certified Wood.
Implementation:
Establish goals for
recycled content during the design phase and
include them in the project specifications.
Doing so is not a requirement, but it can
help in achieving the credit. Many standard
materials contain recycled content because
of how they are manufactured; examples are
steel, gypsum board and acoustical ceiling
tile. Design and construction teams may need
to research which materials contain high
levels of recycled content or verify which
models of a certain product line feature the
desired recycled content; examples include
carpet and ceramic tile. |
|
MR 5
Regional Materials
1-2 points
|
Intent:
To increase demand for
building materials and products that are
extracted and manufactured within the
region, thereby supporting the use of
indigenous resources and reducing the
environmental impacts resulting from
transportation.
Requirements:
Use building materials
or products that have been extracted,
harvested or recovered, as well as
manufactured, within 500 miles of the
project site for a minimum of 10% or 20%,
based on cost, of the total materials value.
If only a fraction of a product or material
is extracted, harvested, or recovered and
manufactureed locally, then only that
percentage (by weight) may contribute to the
regional value. The minimum percentage
regional materials for each point threshold
is as follows:
|
Regional Materials |
Points |
| 10% |
1 |
| 20% |
2 |
Mechanical, electrical and plumbing
components, and specialty items such as
elevators cannot be included in this
calculation. Include only materials
permanently installed in the project.
Furniture may be included if it is included
consistently in MR Credit 3: Materials Reuse
through MR Credit 7: Certified Wood.
Implementation:
The point of
manufacture is considered the place of final
assembly of components into the building
product that is furnished and installed by
the tradeworkers. It may require careful
research to determine what local products
are available, so evaluate this credit early
in the design process. This credit is
achieved by summing the cost of all
materials that are extracted and
manufactured within 500 miles of the
construction site. If the material contains
components that were sourced from a place
within 500 miles but he final assembly was
farther away, the product cannot be counted
toward the credit. In cases where products
and construction components are assembled
on-site, the individual components that are
extracted within 500 miles of the site will
be counted toward this credit.
The general contractor should work with
subcontractors and suppliers to verify
availability of materials that are
extracted, harvested, or recovered and
manufactured locally. The contractor should
run preliminary calculations based on the
construction budget or schedule of values
during the preconstruction phase. This will
allow the construction team to focus on
those materials with the greatest
contribution to this credit as early as
possible. |
|
MR 6
Rapidly Renewable Materials
1 point
|
Intent:
To reduce the use and
depletion of finite raw materials and
long-cycle renewable materials by replacing
them with rapidly renewable materials.
Requirements:
Use rapidly renewable
building materials and products for 2.5% of
the total value of all building materials
and products used in the project, based on
cost. Rapidly renewable building materials
and products are made from plants that are
typically harvested within a 10-year or
shorter cycle.
Implementation:
Establish a goal for
the use of rapidly renewable materials early
in the design phase, identify possible
building materials that may be substituted
with rapidly renewable products, and find
vendors that can achieve this goal. Identify
products and vendors in the project
specifications and plans and work with the
general contractor to source acceptable
alternatives. During construction, make sure
that the specified rapidly renewable
materials are installed. Examples of rapidly
renewable materials include bamboo flooring
and plywood, cotton batt insulation,
linoleum flooring, sunflower seed board
panels, wheatboard cabinetry, wool
carpeting, cork flooring, bio-based paints,
geotextile fabrics such as coir and jute,
soy-based insulation and form-release agent,
and straw bales. |
|
MR 7
Certified Wood
1 point
|
Intent:
To encourage environmentally
responsible forest management.
Requirements:
Use a minimum of 50%
(based on cost) of wood-based materials and
products that are certified in accordance
with the Forest Stewardship Council's
principles and criteria, for wood building
components. These components include at a
minimum, structural framing and general
dimensional framing, flooring, sub-flooring,
wood doors and finishes. Include only
materials permanently installed on the
project. Wood products purchased for
temporary use on the project (e.g.,
formwork, bracing, scaffolding, sidewalk
protection and guard rails) may be included
in the calculation at the project team's
discretion. If any such materials are
included, all such materials must be
included in the calculation. If such
materials are purchased for use on multiple
projects, the applicant may include these
materials for only one project, at its
discretion. Furniture may be included if it
is included consistently in MR Credit 3:
Materials Reuse, through MR Credit 7:
Certified Wood.
Implementation:
Establish a project
goal for FSC-certified wood products and
identify suppliers that can achieve this
goal. Research the availability of the wood
species and products that they want to use,
and make sure that they are available from
FSC-certified sources. Another method for
lowering the impact of wood resources is to
research and specify quality grades that are
most readily available from well-managed
forests. Using lower grades of wood can
dramatically reduce pressure on forests,
which produce only limited quantities of
top-grade timber. Contact local vendors,
suppliers and manufacturers that provide FSC-certified
products as early as possible. |
|
|
|